Modifying Calendar Days

Modify calendar days to account for work or nonwork days or hours that are different than the standard hours defined on the Standard Work Week tab. For example, if you are using a personal calendar, you might choose to specify vacation days by setting the standard working days to nonworking days.

To modify work or nonwork calendar days:

  1. Click Administration.
  2. On the Administration navigation bar, click Enterprise Data.
  3. On the Enterprise Data page, expand Resources and click Resource Calendars.
  4. On the Resource Calendars page:
    1. Click on the calendar you want to modify.
    2. Click the Calendar tab.
    3. On the Calendar tab, click the Date list for a date and select Set to Standard or Nonwork.
  5. Click Save.

Tips

The (globe) on calendar days indicates exception days in the base calendar. You can modify these exceptions days and the globe will disappear. If you set the calendar day back to standard, the Global exception day will reset and the globe will reappear.

Related Topics

Configuring Resource Calendars

Assigning a Base Calendar to a Resource Calendar

Assigning a Resource to a Resource Calendar

Setting Work Hours Per Time Period for a Resource Calendar

Configuring the Standard Work Week for Resource Calendars

Changing the Calendar Type

Resource Calendars Page



Legal Notices | Your Privacy Rights
Copyright © 1999, 2020

Last Published Friday, October 1, 2021