Configuring Summarization Periods

Perform the steps below to specify the interval by which to summarize and store resource spreads.

To configure summarization period settings:

  1. Click Administration.
  2. On the Administration navigation bar, click Application Settings.
  3. On the Application Settings page, click Services.
  4. In the Summarization Periods section:
    1. Select the By Calendar option, the By Financial Periods option, or both.
    2. If you select By Calendar, select a time interval value for the WBS Level and Resource/Role Assignment Level fields.
    3. Click Save.

Tip

Rather than spreading units and costs evenly throughout the length of a project (when you select By Calendar), you can also view how actual units and costs were incurred by selecting By Financial Periods. You can then store and edit period performance for any predefined financial period.

Related Topics

About Application Settings

Working with Application Settings

Configuring Audit Settings

Configuring Clickable Websites

Configuring Data Limits Settings

Configuring Earned Value Settings

Configuring Eventing Settings

Configuring General Settings

Configuring ID Lengths Settings

Configuring ID Lengths Settings

Configuring Report Settings

Configuring Timesheets Settings

Configuring Time Periods Settings



Legal Notices | Your Privacy Rights
Copyright © 1999, 2020

Last Published Friday, October 1, 2021