Assigning Yourself to an Activity

Assign your resource to an activity so that you can add the activity to a timesheet.

  1. Select Timesheets
  2. Select Actions, Assign Activity.
  3. In the Assign Activities box:
    1. Select the project you want to assign yourself to.

      Note: A project-level setting determines whether a project is listed so you can assign yourself to its activities. If you need to assign yourself to a project that is not listed, contact your project manager or P6 administrator.

    2. Select one or more activities.

      Note: You can filter the list of activities in by selecting Activity Name or Activity ID in the Search list, entering text in the for box and selecting Go.

    3. Select Assign & Add to assign your resource to the activities and add the activities to your timesheet, or Assign to assign your resource to the activities without adding them to your timesheet.

Step me through...

Opening a Timesheet

Adding Activities to a Timesheet

Removing Activities from a Timesheet

Recording Actual Work Time on a Timesheet

Reporting a Completed Assignment

Editing Other Resource's Timesheets

Adding or Viewing Timesheet Notes

Saving or Printing a Timesheet

Submitting a Timesheet

Learn more about...

Working with Timesheets



Legal Notices | Your Privacy Rights
Copyright © 2011, 2020

Last Published Wednesday, December 2, 2020