Reporting a Completed Assignment

When you finish a work assignment, if your project allows, you can mark the assignment as completed.

Note: Completing an activity in a timesheet will not apply an Actual Finish to the activity. The actual finish will be applied in the project in P6 after the Project Manager runs Apply Actuals.

To report a completed activity assignment:

  1. Select Timesheets and open a timesheet.
  2. Select an activity.
  3. Select Mark Activity Complete (Ctrl+Alt+C).

Step me through...

Opening a Timesheet

Adding Activities to a Timesheet

Removing Activities from a Timesheet

Assigning Yourself to an Activity

Recording Actual Work Time on a Timesheet

Editing Other Resource's Timesheets

Adding or Viewing Timesheet Notes

Saving or Printing a Timesheet

Submitting a Timesheet

Learn more about...

Working with Timesheets



Legal Notices | Your Privacy Rights
Copyright © 2011, 2020

Last Published Wednesday, December 2, 2020