When you finish a work assignment, if your project allows, you can mark the assignment as completed.
Note: Completing an activity in a timesheet will not apply an Actual Finish to the activity. The actual finish will be applied in the project in P6 after the Project Manager runs Apply Actuals.
To report a completed activity assignment:
- Select Timesheets and open a timesheet.
- Select an activity.
- Select Mark Activity Complete (Ctrl+Alt+C).