Changing Start Dates

You (the portfolio planner) can change the start dates of planned projects, but you cannot change the start dates of the projects that are in execution stage.

When you change a start date, Unifier shifts the end date to preserve the project duration. Unifier also shifts the cash flow numbers (excluding pre-actuals) left, or right, to preserve the cash flow distribution.

To change a start date:

  1. Double-click the date in the Start Date column. Unifier displays a calendar.
  2. Choose the new date from the calendar and press the Enter key on your keyboard.

Unifier shifts the end date and the cash flow numbers to reflect the change.

Before date change:

After date change:

How Unifier Distributes Cash Flow

Unifier stores all cash flow amounts by month in the database. The logic Unifier uses to distribute cash flow dollars is rendered in monthly allocations and presented as follows: