Note: If the user gets any of the permissions below, then the user can access the Activity Sheet node, in the User mode.
To enable the users create, modify, and view the activity sheets, where the user can manually create project schedules, go to the shell, Admin mode and:
- From the left-hand Navigator, click Access Control.
- In the Access Control log, click to expand the User Mode Access.
- Click Activity Manager to expand.
- Click Activity Sheet to open the Permissions Setting for: Activity Sheet window.
- Select from the following permission settings:
- Send System Activity Sheet Data
To send data to the source from system activity sheet
- Get System Activity Sheet Data-All
To create, update, delete, and view all sheets.
- Get System Activity Sheet Data-Current
To create, update, delete, and view all sheets.
- Get System Activity Sheet Data-Current
- Modify System Activity Sheet-All
To update the system activity sheet.
- Modify System Activity Sheet-Current
To update the system activity sheet.
- Modify System Activity Sheet-Current
- View System Activity Sheet-All
To view the system activity sheet.
- View System Activity Sheet-Current
To view the system activity sheet.
- View System Activity Sheet-Current
- Full Access
To create, update, delete, and view all sheets. A user with Full Access permission can view the sheets created by others (for additional schedules) within the project.
- Create Manual Activity Sheets
To create, update, delete, and view all sheets. The system activity sheet cannot be deleted.
- View
- Create Manual Activity Sheets