The Schedule Manager needs attribute forms to define the activities for a project schedule, including its start and end dates.
When creating new activities on the schedule sheet, Unifier opens this form as the General tab of the Activity Properties form.
Note: If there is no attribute form for the Schedule Manager, Unifier will create a default schedule sheet with the following columns: ID, Activity name, Start date, Finish dates, and Duration.
The Resource Manager and the Schedule Manager can work together for resource management. If you have deployed the Resource Manager, Unifier uses the Resource Assignment Attribute form as the Resource tab of the Activity Properties form.
To import and deploy a schedule attribute form or a resource assignment attribute form into Unifier Production environment, see Importing Configuration Packages.