Schedule sheet toolbar

You can perform the following functions from the toolbar. Click the down arrow next to a button to view further options.

Button

Action

Save

Saves changes made to the schedule sheet.

Add

Click the arrow next to the button and choose one of the options:

Manual: Add a row (activity) manually.

Copy Activity From: Add a row by copying a row in a selected sheet.

Delete

Select a row and click Delete to delete the activity.

Indent

Select a row and click to indent the row. The row above become a summary row.

Outdent

Select an indented row and click to out-dent.

Gantt

Return to the Gantt chart view.

Progress

Access the Activity Progress view. See Entering Progress in the Activity Progress Window for details on activity progress.

Columns

Add and manage columns on the sheet.

Find

Click to search for an activity. You can search on any column on the sheet.

Zoom In

Click to zoom in the Gantt chart. The default view is week (by day), which is the maximum zoom-in view.

Zoom Out

Click to zoom out the Gantt chart. You can zoom out to month (by week) view and year (by month) view.

Focus

Select an activity and click to move the activity into focus. The Gantt chart view moves to the beginning date of the selected activity.

Close Window

Close the schedule sheet.



Legal Notices | Your Privacy Rights
Copyright © 1998, 2022

Last Published Monday, April 11, 2022