Purpose
The analysis shows labor units and cumulative labor units broken down by date. Use the Select a View list to determine whether the content displays as a chart or table. The chart and the table display the same information.
The line-bar chart shows:
- Bars for Baseline Project Labor Units, At Completion Labor Units, and Actual Labor Units Cumulative
- Lines for Actual Labor Units, Baseline Project Labor Units Cumulative, and Forecast Labor Units Cumulative
The x-axis shows the year and month. The y-axis for the bars, on the left, shows labor Units. The y-axis for the lines, on the right, shows labor Units (Cumulative). Hover over a bar or a point on a line to see detailed information.
The pivot table breaks data down by month and resource. The data is ordered by month. The pivot table contains columns for:
- Month Name
- Resource Name
- Baseline Project Labor Units
- Actual Labor Units
- At Completion Labor Units
- Baseline Project Labor Units Cumulative
- Actual Labor Units Cumulative
- Forecast Labor Units Cumulative
Click on a month name to drill down to weekly data. Use the up and down arrows below the table to navigate to other sections of the table. Use the double-ended arrow to view the whole table in one screen (to a maximum of 500 rows per page).
Location
- On the Home page, click Dashboards.
- Under Primavera, select Resource Analysis.
- On the Resource Analysis dashboard, click the Productivity page.
- On the Productivity page, expand the Periodic and Cumulative Labor Units by Month section.
Subject Area
Activity