Configuring Benchmarking Groups for P6 Projects

In CIC Advisor, projects can be compared and contrasted with two benchmark groups on the Benchmark Detail page.

To set up benchmarking groups in CIC Advisor to compare your P6 project with:

  1. Sign in to the CIC Administration application.

    http://<host>:<port>/cicadmin

  2. From the Icon_Home_menu_in_admin_app_home_page Home menu, select a staretl<id> or a <Custom Name for DataSource>.

    Note: <id> is the identifier of the data source.

  3. In the sidebar, click Benchmark Benchmark.
  4. Click Model Name Icon Edit and enter a name for each baseline group being created.

    Note: You can set up only two benchmark groups with a maximum of 7 projects in each group that are either complete, or 85 - 90% complete.

  5. Populate each group with projects as follows:
    • To add a project to a baseline group, select a project from the list of available projects brought over by the ETL, and drag and drop it into a baseline group.
    • To remove a project from a baseline group, select a project in a baseline group and delete it from the baseline group.
  6. Click Save to create baseline groups for benchmarking.

Related Topics

CIC Advisor for P6 EPPM

Roadmap for Configuring CIC Advisor for P6

Configuring P6 EPPM Data Sources

Running ETLs and ODI Loads for P6 EPPM Data Sources

Reviewing the Status of P6 Publication Services

Configuring Threshold Settings for P6 Data

Creating Custom Project Groups to Train Models



Last Published Monday, July 1, 2024