Overview Section
The Overview section of the Schedule Intelligence page provides a synopsis of the current state of the project and the predicted project end date based on the project's current schedule in P6.
The following information is displayed:
- Schedule Status: The current status of your project.
If the project is 95% and above completed, the status displays as Completed.
If the percent completion is 0, then the status is displays, Not Started.
For all the other cases, the status displays In Progress.
- Milestones: A milestone represents a significant project event of zero duration. Displays a count of the total milestones in the project, the number of milestones met, and delayed milestones in the project.
- Planned start date: The date the project is scheduled to start as per the current project schedule.
- Predicted end date: The date the project is planned to finish as per the current project schedule.
- Baseline start date: The actual scheduled start date of an activity in the approved schedule baseline.
- Baseline end date: The finish date of a schedule activity in the approved schedule baseline.
- Predicted end date: The potential end date of the project as predicted by CIC Advisor.
- Project owner: The individual responsible for the successful implementation of the project, in partnership with the sponsor.
- Last milestone met: The most recent milestone met by the project.
- Project late by: The actual delay of the project in terms of days. number of days by which the project was completed late from the planned end date.