Leveling Project Resources

Level one or more projects whenever the required shared or critical resources have limited supply or availability or to generally keep resource usage at a constant level. For example, when a resource has been assigned to more than one activity during the same time period, level the projects to eliminate potential resource over-allocation. Once you have performed resource leveling against your project or projects, you will be able to see where resources are overallocated and make decisions about whether work assigned to some resources should be redistributed to other available resources.

To level resources in one or more projects:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page:
    1. Click Actions and select Leveler.
    2. In the Level Resources dialog box:
      • Configure resource leveling options.
      • Select the Resources tab to specify which resources should be leveled.
      • Select the Prioritization tab to specify which assignments are leveled first when a conflict exists.
      • (Optional) Click Save to save your settings and close the dialog box.
      • Click Level Now.

Tips

Related Topics

About Resources

Assigning Resources to an Activity

Assigning Resources to Multiple Activities

Configuring Activity Resources

Assigning Locations to Resources

Adding Activity Resource Estimates

Specifying Resource Assignment Rates

Assigning Resource Curves to Resource or Role Assignments from the Activities Page

Assigning Resources to Unstaffed Activities

About the Recalculate Assignment Costs Feature

Configuring Resource Leveling Options and Priorities

About the Check Resource Overallocation Service

About Resource Assignments



Legal Notices | Your Privacy Rights
Copyright © 1999, 2021

Last Published Monday, December 6, 2021