Assigning Resources to an Activity

Perform these steps to assign one or more resources to an activity.

To assign resources to an activity:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page, select an activity and click the Assignments detail window.
    1. In the Assignments detail window, click Assign... and select Resource.
    2. In the Select a Resource dialog box:
      • Select one or more resources.

        Note: Click Show Usageto show the usage spreadsheet and histogram for the selected resource and optionally change the Start and Finish fields to customize the visible portion of the usage chart. The usage spreadsheet and histogram show the first resource you selected if you select multiple resources.

      • Click Assign.
    3. Confirm whether you want to send an email notification to the affected resources.

Tips

Related Topics

About Resources

Assigning Resources to Multiple Activities

Configuring Activity Resources

Assigning Locations to Resources

Adding Activity Resource Estimates

Specifying Resource Assignment Rates

Assigning Resource Curves to Resource or Role Assignments from the Activities Page

Assigning Resources to Unstaffed Activities

About the Recalculate Assignment Costs Feature

Configuring Resource Leveling Options and Priorities

Leveling Project Resources

About the Check Resource Overallocation Service

About Resource Assignments



Legal Notices | Your Privacy Rights
Copyright © 1999, 2021

Last Published Monday, December 6, 2021