Schedule of Values (SOV) Sheets and Business Processes

This section discusses how to manage BP records, including searching for existing BPs, transferring ownership, viewing BP properties, and viewing Schedule of Values (SOV) or funding information from within a Cost type BP.

View an SOV sheet from the BP form

Commit (contract) or spend (invoice) BPs can be set up to automatically create a Schedule of Values (SOV) sheet. These transactions can be easily accessed directly from the BP form. The BP form remains active.

If the BP has been set up to automatically create an SOV sheet, an SOV button appears at the top of the BP form after the SOV sheet has been created.

For more information about Schedule of Values (SOV) sheets, see the Unifier Managers User Guide (Cost Manager, About Schedule of Values (SOV)).

To view the SOV sheet created from the Cost type BP:

  1. Wait for the BP to reach terminal status.
  2. Open the business process and click the Menu Options ( ).
  3. Click SOV to open the SOV sheet that corresponds to the transaction.
  4. Close the SOV sheet to return to the BP form.

Create SOV breakdowns

You can add SOV breakdowns from this view. Breakdowns are only in use in the SOV sheet, not the cost sheet. If another transaction exists for the CBS code, you will not be able to do a breakdown.

To add CBS code breakdowns that can be used to create invoices:

  1. Open the business process and click the Menu Options ( ).
  2. Click SOV to open the SOV sheet that corresponds to the transaction.
  3. Click a listed CBS code from the sheet. The CBS Detail window opens.
  4. Go to the Breakdown tab in the right pane.

For more information about adding CBS breakdowns, refer to the Unifier Managers User Guide (Cost Manager, Adding Breakdowns to SOV sheet by Importing).

View, or edit, fund transaction details from the BP form

Commit (contract) or spend (invoice) BPs can be set up to consume or appropriate funds in the project/shell funding sheet or commitment funding sheet. These transactions can be easily accessed directly from the BP form.

If the BP form has been set up for funding (and is in the appropriate step, and you have funding permissions), a Funding button will appear at the top of the BP form. This lets you perform a fund assignment while routing and approving a BP, such as a payment. Access to this button and fund information is dependent upon your Fund Manager permissions.

For more information, see the About business processes enabled for commitment funding and About business processes enabled for funding topics in the Cost Manager section of the Unifier Managers User Guide.

Composite view of Base Commits and Change Commits

You can view a composite view of both Base Commits and Change commits. The SOV sheet is used as a composite view, and the SOV sheet will be the composite of the PO and all added lines from Change commits.

To support the line-item mode, the SOV sheet has a column called Ref that represents line item numbers.

There are other fixed columns, and the columns will be dependent on the mode.

To view funding details from the Cost type BP:

  1. Wait for the BP to reach terminal status.
  2. Open the business process and click the Menu Options ( ).
  3. Click Funding to open the Funding sheet that corresponds to the transaction.
  4. Review the details of the transaction.

    Note: This is the same window that you would see if you clicked on the link corresponding to this transaction on the project or shell funding sheet.

To reassign funding, click Fund Assignment. For more information, see "About business processes enabled for funding" in the Cost Manager section of the Unifier Managers User Guide.

See Also

Business Processes with Special Behaviors

Payment Application Business Processes

General Spends Business Processes

Change Commit Business Processes

SOV Summary Payment Applications Sheets and Business Processes

SOV Summary Payment Application Business Process

Overpayment in Summary Payment Applications SOV

Base Commit SOV Type

Change Commit Summary Payment Application SOV Type

Totaling Cost Breakdown Values

Request for Bid (RFB) Business Processes

Lease Business Processes

Reservation Business Process

Entering Values in Fields



Last Published Monday, August 28, 2023