Running the Project Checker

Run the Project Checker to assess the health of the data that constitutes projects. The Project Checker looks for data that violates unique and foreign key constraints and business rules. You must be logged in to P6 as a user with the Admin Superuser global security profile to run the Project Checker.

To run the Project Checker:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. Click the Actions menu and select Project Checker.
  4. In the Project Checker dialog box:
    1. In the Project Selection field, select Select
      • In the Select Project dialog box, select the projects to check and click Select.
    2. On the Options list, select the checks to run.
    3. Optionally select the Limit report rows option to reduce the size of the report.

      If you selected to limit the rows returned by the report, in the Maximum Rows field, select the maximum number of rows you want to return for each check in the report.

    4. Select Run.

Tips

Related Topics

Configuring Project Preferences

Configuring History Settings for Analytics

Configuring Project Calculations

Configuring Project Defaults

Configuring General Project Preferences

Configuring Project Summarization and Publication Services

Configuring P6 Team Member Status Update Reviews

Configuring P6 Team Member View Preferences

Configuring Project Preferences for Multiple Projects



Legal Notices | Your Privacy Rights
Copyright © 1999, 2024

Last Published Thursday, July 25, 2024