Configure general project preferences to specify general information concerning the project such as when the fiscal year begins.
To configure general project preferences:
- Click Projects.
- On the Projects navigation bar, click EPS.
- On the EPS page:
- Select a project or EPS node.
Notes:
- If an EPS node is selected, opening the project preferences dialog box always shows the default values for all settings and fields. The selections you make in any fields will be applied to all projects that match the applied filter in the selected EPS node and all child nodes.
If you want to change a setting to the default for all projects that match the applied filter in the selected EPS node and all its child nodes, you must change that setting away from the default and then change it back to the default before applying the changes.
- Click Row Actions and select Set Project Preferences.
- In the Project Preferences dialog box, click General.
- On the General page configure the WBS Code Separator field and select a month for the Fiscal year begins on the first day of list.
- Click OK.