Mark an activity complete when you have finished your work for the activity.
To mark an activity complete:
- Select an activity.
- In the activity pane, select Mark Activity Complete (Ctrl+Alt+C).
- On the Status tab of the progress panel:
- Update the status fields.
- Update the Finished date if the finish date is not the scheduled Finished by date.
Note: You cannot set the Finished date to a date past the current date.
- Select Save.
Tips
- Once you complete an activity, you can return the activity to an active state by selecting Mark Activity In-Progress.
- If your activity entry is a milestone, select Mark Activity Complete (Ctrl+Alt+C) and update the Started date for a start milestone, or the Finished date for a finish milestone.
- If the Update actual units when activities or assignments that were never started are marked complete in My Activities setting is selected in the General section of Application Settings and the activity you mark complete has never been updated, marking the activity complete will update the actual units for the activity to match the planned units.