Updating Activities for Other Resources

Update activities for other resources to record time for resources which do not have access to Team Member. A project-level administrative setting determines whether you can provide status for other resources.

Note: The fields displayed in your view are customized by your project manager. Not all fields mentioned here are available in your view and there may be additional fields in your view not mentioned in the procedure. Discuss with your manager the fields you need to update to provide status on your assignments.

To update an activity:

  1. Select an activity.
  2. On the Status tab of the progress panel, select Status Other Resources.
  3. In the Resources dialog box:
    1. Select a resource from the Resources list.
    2. Enter their status. For example, Time Spent, Time Left, Units Consumed or Units Left.
    3. Update their Finish By date, if necessary.
    4. Select Mark Activity Complete, if the resource has completed work on the activity.
    5. Select Save (Ctrl+Alt+Enter).

Tips

Step me through...

Viewing Activities

Starting Activities

Updating Activities

Sending Email About an Activity

Starring Activities

Completing Activities

Learn more about...

Working with Activities

Field Definitions for Dates and Work Units