Recost - Assignment Attributes
| Assignment Attribute | Data Element | Calculation | 
|---|---|---|
| Planned Cost | 
 | Calculated at spread level. Unifier Planned Units X Price/Unit. If the rate source is Override, then the system uses the rate present in the activity sheet (System or Manual) corresponding to that assignment. | 
| Actual Cost | 
 | Calculated at spread level. Unifier Actual Units X Price/Unit. If the rate source is Override, then the system uses the rate present in the activity sheet (System or Manual) corresponding to that assignment. | 
| Remaining Cost | 
 | Calculated at spread level. Unifier Remaining Units X Price/Unit. If the rate source is Override, then the system uses the rate present in the activity sheet (System or Manual) corresponding to that assignment. | 
| At Completion Cost | 
 | Calculated at spread level. Unifier At Completion Cost is the sum of actual cost and remaining cost for that assignment. | 
See Also
Earned Value Management Attributes
Activity Attributes (Scheduling)
Activity Attributes - Earned Value