Activity Attributes (Units)
| Assignment Attribute | Data Element | Calculation | 
|---|---|---|
| Planned Total Units | 
 | The planned units of work for the activity. | 
| Actual Total Units | 
 | The exact number of units that have been expended on the selected activity. | 
| Remaining Total Units | 
 | The remaining units of work to be performed by the resource on the activity. Calculated as Planned Units minus Actual Units. | 
| At Completion Total Units | 
 | The sum of the actual units and remaining units for the resource assignment on the activity. Calculated as Actual Units plus Remaining Units. | 