Activity Attributes (Cost)
| Assignment Attribute | Data Element | Calculation | 
|---|---|---|
| Planned Total Cost | 
 | The expected total cost of the activity, consolidating costs of all assignments. | 
| Actual Total Cost | 
 | The actual non-overtime plus overtime cost for all the resource assignments of the activity. | 
| Remaining Total Cost | 
 | The remaining cost of all the resource assignments for the activity. | 
| At Completion Total Cost | 
 | The sum of the actual costs plus remaining costs for the resource assignment on the activity. Calculated as Actual Costs plus Remaining Costs. | 