Create a Schedule Sheet

Each schedule sheet that you create has its own set of properties, which you can use to control schedule sheet behavior.

The system separates Schedule Sheet Properties into five tabs; each tab has a distinct purpose.

You can create a project or shell schedule sheet in the following ways:

You can have any number of schedule sheets in a project or shell. You can designate one sheet as a master schedule sheet, which appears in bold in the log. The master schedule sheet drives the activity start and finish dates, and allows you to assign resources to activities. You can use it to track progress and resource assignment information to other modules in the system.

Note: You may want to set up the schedule sheet before selecting it as the master sheet. After you select the sheet as the master sheet, it cannot be deselected.

To create a project or shell schedule sheet manually

  1. Go to the project/shell tab and switch to User mode.
  2. In the left Navigator, click Schedule Manager > Schedule Sheets. The Schedule Sheets log opens.
  3. Click New. The Schedule Properties window opens.
  4. Complete the Schedule Properties tabs. See Schedule Sheet Properties General Tab.

To create a schedule sheet by copying from a project or shell template

  1. Go to the project/shell tab and switch to User mode.
  2. In the left Navigator, click Schedule Manager > Schedule Sheets. The Schedule Sheets log opens.
  3. In the Schedule Sheets log, click Copy > Template.
  4. Select the template to copy and click Open.
  5. Complete the Schedule Properties tabs. See Schedule Sheet Properties General Tab.

To create a project or shell schedule sheet by copying another sheet

  1. Go to the project/shell tab and switch to User mode.
  2. In the left Navigator, click Schedule Manager > Schedule Sheets. The Schedule Sheets log opens.
  3. In the Schedule Sheets log, click Copy. The Schedule Sheets window opens showing all sheets in the project/shell (both active and inactive)
  4. Select the schedule sheet to copy and click Open. The Schedule Sheet Properties window opens.
  5. Complete the Schedule Properties tabs. See Schedule Sheet Properties General Tab.

To import CSV files

  1. Open the schedule sheet.
  2. Choose File > Import > From CSV. If a default mapping is not selected, the Select Data Mapping window opens.
  3. Select the data mapping you want to use for this import and click OK. The File Upload window opens.
  4. Browse to select the file to upload.
  5. Click OK.

To import XML and MPP files

  1. Open the schedule sheet.
  2. Choose File > Import > From External Source. If a default mapping is not selected, the Select Data Mapping window opens.
  3. Use the table below to complete the fields in this window.
  4. Click OK. The File Upload window opens.
  5. Browse to select the file to upload.
  6. Click OK.

In this field:

Do this:

MPP

Data mapping is not required; leave the Data Mapping field empty.

MPP XML

Data mapping is required; select the mapping you want to use.

MPP activity calendar

Select Consider Activity Calendar.

This requires an existing calendar with the same name.

If an activity calendar is not imported and considered, the activity will use the existing calendar defined in the schedule sheet properties.

MPP Resource assignments

Data mapping is not required; leave the Data Mapping field empty. This requires a data set for the SYS Resource Type data element.

Use MPP standard resource types: Work, Material, and Cost. Upon import, the system will soft-book these resource types.

Before you begin:

In This Section

Schedule Sheet Properties General Tab

Gantt Chart tab of the Schedule Sheet Properties

Schedule Sheet Properties: Tracking Gantt Chart tab

Options Tab of the Schedule Sheet Properties

Schedule Tab of the Schedule Sheet Properties

Create a master schedule sheet

Open / Modify schedule sheet template properties

Changes that occur to copied and pasted activities



Last Published Sunday, July 20, 2025