Planning Page of the Resources Section
Overview
Use the Planning page to establish resource demand on a proposed project without the need to perform time-consuming resource-loading on a detailed project plan. Specify, review, or modify project-level and WBS-level allocation data for individual resources and roles across the project lifecycle.
Note: The default filter for this page is Portfolio. If no data appears on the page, you may need to change the filter.
Screen Elements
Assign... menu
Resource: Enables you to assign a resource to a selected project or WBS.
Role: Enables you to assign a role to a selected resource, project, or WBS.
Search For a Resource to Assign: Enables you to search for a resource to assign to a selected project.
Project: Enables you to assign a project to the selected resource or role.
Actions menu
Hide if Empty: Select this option to hide empty rows from the view.
Show Other Assignments: When you have filtered your view to a single resource, role, resource team, role team, or resource code, use this action to see all assignments in the project while maintaining the grouping of your view by the original data item.
Show Only Unassigned Role Requests: enables you to filter the view to show only role assignments that are not yet staffed.
Synchronize Resource Dates: enables you to synchronize the start and finish dates of planning assignments with project dates. To synchronize resource dates, group your view by project. You can choose whether to synchronize:
- The dates of all assignments that have the Life of Project option selected with the scheduled start and finish dates of the project.
The dates of all planning assignments with the project's Forecast Start and Forecast Finish dates. If there is a difference between the Project Forecast Start and the Forecast Start Date, that difference is added to the start and finish date of all assignments.
Grid View
Enables you to view and configure data in a grid format. You can customize which columns are available in the grid.
Spreadsheet View
Enables you to view data as a spreadsheet.
Filter By
Opens the Filter By dialog box. Use this dialog box to filter and select the data you want to display on the Resource Planning spreadsheet.
Full Screen
Expands the current work area so it fills the entire display.
Opens the Print Options dialog box.
Customize View
Opens the Customize View dialog box.
Refresh
Refreshes the current screen with any new, updated, or removed data.
Search
Searches the view or dialog box for data matching the criteria entered into the box.
Planning work area
The main work area for planning assignments to projects in your choice of the following customizable formats:
- Grid View Format of the Planning Page of the Resources Section
- Spreadsheet View Format of the Planning Page of the Resources Section
Download
Enables you to download the data as an Excel file. For hierarchical data, the top level and any expanded levels are downloaded. For flat lists, all rows are downloaded.
Tips
- At the portfolio, project code, and project levels, the Total Units column and timescale interval columns display a summary total of allocated units for all resources and roles. For example, if you choose a project when filtering the spreadsheet by projects, allocated units of all resources belonging to a given project roll up and show summary totals in the Total Units column and timescale interval columns in the spreadsheet for the project's row.
Getting Here
- Click Resources.
- On the Resources navigation bar, click Planning.
Related Topics
Assigning Projects or WBS Elements to Resources or Roles
Assigning Resources or Roles to Projects or WBS Elements
Allocating Units to Resources or Roles
Allocating Units by Spreading Units Across a Time Period
Exporting the Planning Spreadsheet