Assigning Projects or WBS Elements to Resources or Roles

You can assign a project or WBS elements to resources on the Planning page when the spreadsheet is filtered by resource, resource team, or resource code. You can also assign a project or WBS to roles when the spreadsheet is filtered by role or role team.

To assign a project or WBS to a resource or role:

  1. Click Resources.
  2. On the Resources navigation bar, click Planning.
  3. On the Planning page, select a resource or a role.
  4. Click Assign..., and select Project.
  5. In the Select Project dialog box:
    • To assign a project, select the project you want to assign, then click Assign.
    • To assign a WBS, select the project from the projects list, then click Assign WBS. In the Select Parent dialog box, select the WBS you want to assign, then click OK.
  6. On the Planning page, click Save.

Related Topics

Resource Planning

About Resource Planning

Assigning Resources or Roles to Projects or WBS Elements

Searching for a Resource to Assign

Allocating Units to Resources or Roles

Allocating Units by Spreading Units Across a Time Period

Splitting Resource Assignments

Exporting the Planning Spreadsheet

Planning Page of the Resources Section



Last Published Wednesday, July 10, 2024