Splitting Resource Assignments

During your planning, you might find that some resources become overloaded with work. One way to resolve overallocation of units to a resource is to assign some of its total units to another resource.

To split resource assignments:

  1. Click Resources.
  2. On the Resources navigation bar, click Planning.
  3. For the overloaded resource, select Row Actions menu, select Split Resource Assignments.
  4. In the Split Resource Assignments dialog box
    1. Select a resource from the list.
    2. In the Percentage allocation to new Resource field, enter a percentage of the original resource's total units to re-assign.
    3. Click Assign.

Related Topics

Resource Planning

About Resource Planning

Assigning Resources or Roles to Projects or WBS Elements

Searching for a Resource to Assign

Assigning Projects or WBS Elements to Resources or Roles

Allocating Units to Resources or Roles

Allocating Units by Spreading Units Across a Time Period

Exporting the Planning Spreadsheet



Last Published Wednesday, July 10, 2024