Standard Work Week Tab of the My Calendar dialog box or Resource Calendars Page

Overview

Use this tab to specify the length of work hours in a day or to calculate the total number of hours worked in a particular day.

Screen Elements

Print

Opens the Print Options dialog box.

Total Hours field

The total number of work hours for each day.

Calendar View area

Enables you to view a day, week, month, or year of the calendar to identify standard time, nonwork time and calendar exceptions.

Work Period display

Displays a box that represents each work period in a day. If you change the number of hours covered by the work period boxes for a day, P6 updates the Total Hours field.

Tips:

Getting Here

From the Enterprise Data page:

  1. Click Administration.
  2. On the Administration navigation bar, click Enterprise Data.
  3. On the Enterprise Data page, expand Resources and click Resource Calendars.
  4. On the Resource Calendars page, click the Standard Work Week tab.

From the My Calendar dialog box:

  1. Click the User menu and select My Calendar.
  2. In the My Calendar dialog box, select the Standard Work Week tab.

Related Topics

About Calendars

Working with Calendars

Creating Resource Calendars

Configuring Resource Calendars

Assigning a Base Calendar to a Resource Calendar

Assigning a Resource to a Resource Calendar

Setting Work Hours Per Time Period for a Resource Calendar

Configuring the Standard Work Week for Resource Calendars

Modifying Calendar Days

Changing the Calendar Type



Last Published Wednesday, July 10, 2024