Used By Tab of the Resource Calendars Page
Overview
Use this tab to view resources assigned to the resource calendar.
Screen Elements
Opens the Print Options dialog box.
Search
Searches the view or dialog box for data matching the criteria entered into the box.
ID field
The ID of the project, activity, or resource assigned to the calendar.
Name field
The name of the resource assigned to the calendar.
Tips
- Resources must be assigned calendars irrespective of their assignment to activities or projects.
Getting Here
- Click Administration.
- On the Administration navigation bar, click Enterprise Data.
- On the Enterprise Data page, expand Resources and click Resource Calendars.
- On the Resource Calendars page, click the Used By tab.
Related Topics
Configuring Resource Calendars
Assigning a Base Calendar to a Resource Calendar
Assigning a Resource to a Resource Calendar
Setting Work Hours Per Time Period for a Resource Calendar
Configuring the Standard Work Week for Resource Calendars