Applying Actuals to a Project

Apply actuals to update progress on the currently selected projects as of the specified data date.

To apply actuals:

  1. Click Projects.
  2. On the Projects navigation bar, click Activities.
  3. On the Activities page:
    1. Click Actions and select Apply Actuals.
    2. In the Apply Actuals dialog box:
      • Select the projects to which you want to apply actuals.
      • Select a date from the New Data Date calendar.
      • Select an option from the Remaining Duration Calculation list.
      • Click Apply.

Tips

Related Topics

About The Apply Actuals Feature

Working with the Apply Actuals Feature

Applying Actuals Based on the Auto Compute Actuals Method

Applying Actuals Based on the Timesheets Method

Creating Project Scheduled Services