- Overview
- Configuring Project Management Bridge after Installation
- The Project Management Bridge Menu
- Importing Projects
- Bridge Console
- Project Management Systems Server List
- Status Area
- PM Bridge Console Operation
- Adding a PM Server
- Checking Server Status
- Editing the PM Server Configuration
- Removing a PM Server
- Synchronizing Projects from a PM Server
- Importing Projects from a PM Server
- Accessing a PM Server's Web Interface
- Viewing a PM Server Log
- Printing the PM Server Configuration Report
- Loading PM Server Settings
- Saving PM Server Settings
- Viewing the System Log
- Setting the Synchronization User
- The Project Management Bridge Wizard for P6
- Setting up the PM Bridge
- Step 1: Accessing the Bridge Server Settings Wizard
- Step 2: Entering General Bridge Server Settings Information
- Step 3: Entering Defaults Information
- Step 4: Sub-Items Mode — Entering Mapping Defaults
- Step 5: Sub-Items Mode-- Entering Publish Mapping Definitions
- Step 6: Sub-Items Mode -- Entering Update Mapping Definitions
- Step 7: Phases Mode — Entering Mapping Defaults
- Step 8: Phases Mode— Entering Publish Mapping Definitions
- Step 9: Phases Mode— Entering Update Mapping Definitions
- Viewing Information from the Project Management System
- Available P6 Fields
- P6 Project level fields available for update Items and Portfolios
- P6 Project level fields available for publish
- P6 WBS level fields available for update
- P6 WBS level fields available for publish
- P6 Spreadsheet fields available for Update
- P6 Resource fields available for spreadsheet selected resources filter
- Copyright