Reprocessing a Block

Access the SPED Job Revision form.

You can reprocess a block only if the block status is D (done).

  1. Select the block to reprocess, and select Select/Unselect Block from the Row menu.

    The system places a check mark next to the block and the UBEs for the block.

  2. From the Form menu, select Process.

    The system reprocesses the selected block.

Important: If you reprocess a block (selected the block), you must also reprocess subsequent blocks that use the data that you regenerated. For example, the Block 9 Generation program (R76B846) reads data from blocks 0, I, J and M.