Demand Flow

Select the Demand Flow tab.

Demand Flow Product

Select to designate the item as an end item. You can add an item to a mixed model family only if this check box is selected.

Total Product Cycle Time

This field is populated when the total product cycle time for this product is calculated.

Primary Line

Select the line where the item is produced primarily. You set up lines in the Line Master program (PF30L912). If you specify integration with JD Edwards EnterpriseOne Manufacturing for your scenario, the system validates the primary line as a work center. When you enter the primary line, the system automatically populates the Work Center field and the Work Center Branch/Plant field.

Work Center and Work Center Branch/Plant

If you specify integration with JD Edwards EnterpriseOne Manufacturing for your scenario, the system automatically populates these fields when you enter a primary line. The system retrieves the values from the line master record of the primary line.

If you do not integrate JD Edwards EnterpriseOne Demand Flow Manufacturing with JD Edwards EnterpriseOne Manufacturing, these fields do not appear on the form.

Explode BOM (explode bill of material)

Select to indicate that the bill of material for the item should be exploded to extend the demand by the quantity per from the bill of material.

Kanban Controlled Item

Select to indicate that the item is kanban controlled. If the item is kanban controlled, size calculations are performed for single or dual cards.