Add Time or Labor

When you open the Debrief page, Labor Hours and Travel Time is displayed automatically.

You can use the Labor option to add the time you have spent on an activity, including any overtime.

Calculation of Labor Hours and Travel Time

Labor Hours Calculation

Labor hours are determined by the difference between the activity start time and the activity end time.

If the activity end time is earlier than the time when the resource opens the Debrief plugin (before saving the debrief entries), the labor hours are calculated as the difference between the activity start time and Debrief plugin opening time.

Travel Time Calculation

Travel time is calculated as follows:

  • Travel Start Time: Calculated by subtracting the travel duration from the activity start time.
  • Travel End Time: Defined as the activity start time.

The difference between the travel start time and travel end time is recorded as the travel time.

You can also update the values of Labor hours and Travel time as well. You can override the auto populated values and create new values in the Debrief page.

You can use the Add Charges option to add the time you have spent on an activity, including any overtime.

  1. Sign in to Oracle Fusion Field Service.
  2. Start the required activity. Or, open a started activity.
  3. Click Debrief on the Activity Details page.
  4. Click the Add Charges drop-down list and select Labor.
  5. Complete these fields:
    Field Action
    Billing Type Select the service for which you are adding labor. For example, Repair.
    Billing Item Select the sub-type for which you are adding labor. For example, Overtime.
    Start Time Select the time at which you started the activity.
    End Time Select the time at which you ended the activity.

    Duration shows the difference between the start and end times and displays two decimal places for fractional hours. This is to support the rate, which is defined as the amount of money per hour.

  6. Click Submit.