Activity and Segment Duration Adjustment

You can adjust the duration of activities and the individual segments that comprise them. The duration of the complete task is set up while creating a segmentable activity. You must adjust the Time to complete value to adjust the activity and segment durations.

When you first create a scheduled segmentable activity, it is automatically split into segments. The duration of each segment is calculated according to the constraints and the actual time available in the route of the resource. You can adjust the activity and segment duration based on these constraints, however, the purpose, procedure and results of such adjustments may be different.