On the List view, you can select the segments of scheduled segmentable activities for
group actions, together with other activities in the route. In this case, only
Change and Cancel actions are available, the
Move action is not available.
- Open the segmentable activity in the List view and select the activities you want to move.
If you select other activities with segmentable activity segments,
the Move link is shown, but the move action
is applicable only to the other activities. Further, the count of
activities denotes the number of other activities.
The hint appears denoting the number of segments available
to change and cancel and the other activities to move.
- Select the appropriate option:
Option |
Description |
Change |
When you apply this option to one or more pending segments, the details of the
entire segmentable activity are updated. If you change the segment with start status, the
updates are visible only to the selected segment. If you change a pending segment, the
entire activity is updated. |
Cancel |
You can cancel only the pending segment and not the entire activity. You also
cannot update the time to complete the segment when you cancel the segments. When you
cancel a group of activities, the route is not recalculated until you cancel all
activities selected for the operation. This reduces the time required for the operation
and increases the application’s performance. |
The selected segments are changed or cancelled.