Use Planned Capacity for Booking Activities

You can book activities using planned capacity either from Day 1 of the calendar or use the planned or available capacity based booking approach for booking on a short term.

Before you start

Ensure that you select the Booking Interval based option under the Manage quota as section to use planned capacity for booking.
Recommendations:
  • If your calendars are accurate only for few days, use available capacity for this period and then switch to planned capacity.

  • For planned capacity, use quota per capacity category to imitate distribution of your work force work skills.

  • For planned capacity, close unneeded booking intervals in advance to imitate distribution of your work force schedules. If possible, maintain the total length of open booking intervals close to work day length to avoid unnecessary over or under booking.

Note: Quota based on working time plans is only supported, if quota is managed based on booking intervals and is not supported for time slot based quota. Planned capacity is an equivalent of the "working time plans", which you can set on the Available Capacity screen or through the API. Also, working time plans are accessible through the Admin interface.

To use planned capacity for booking activities:

Here's what to do

  1. Select the Enter quota as a percent of planned capacity option for daily quota configuration.
  2. Select the Enter quota as % of capacity available by calendar and enter the number of days in the next days and switch to the plans field to use the available capacity for a specified number of days and switch to planned capacity after the specified days.
    For example, if you enter 0 in the next days and switch to the plans field, then it means that you want to use the available capacity to book activities. If you enter 1, it means that during the first day (that is, today), the available capacity is used and the planned capacity is used from tomorrow. The logic is to use the planned capacity from the day after the specified number of days until the overnight time setting value is met. If the number of available resources is different from the working time plan resources, then the available capacity is used for booking and may lead to over or under booking of activities.
    Note: If no working time plans are set, then the available capacity is used as planned capacity. Working time plans can be set in absolute time units (minutes/hours/days) or in number of resources. If resources are used for plans, the value, ‘Number of hours per man-day’ is used to convert the number of resources into hours (and then to minutes, if required).
  3. Click Save.

Results:

The available capacity is distributed between capacity categories and booking intervals according to real schedules; whereas, the planned capacity is proportionally distributed between available booking intervals and copied for all the capacity categories.
For tomorrow, assume that there are plans for 10 resources. The following list of categories are available: Install, Uninstall, Trouble Calls. The booking intervals defined in the system are: [8-12], [13-17]. In this case, the total amount of planned working time is 80 man-hours (that is, 10 resources * 8 hours working day). The planned working time distributes as follows:
Capacity Category 8 - 12 13 - 17
Install 40 40
Uninstall 40 40
Trouble Call 40 40
Note that the total working time plans are distributed proportionally on all intervals for which the booking is not closed on the interval level in advance. If the intervals [0-8] and [17-24] are included, then the planned working time distributes as follows:
Capacity Category -8 8 - 12 13 - 17 17 -
Install 28 14 14 24
Uninstall 28 14 14 24
Trouble Call 28 14 14 24

Therefore, around two-third of the overall time is reserved for the morning and evening intervals even though there are probably no resources working (assuming that the overnight setting in the business rules page is set to 0). If the overnight settings are set to non-zero value, the -8 interval has a length of 8 hours (that is, starting at beginning of day), but the 17- interval prolongs till overnight end, so the length of the interval is increased with the overnight settings value.

To overcome the issue from last example, you can use the following strategies:
  • Delete the non-working intervals from the overall intervals list, if the companies/buckets have stable work hours.

  • Close booking on the non-working intervals in advance (over the period defined for quota calculation in the business rules).