Time to Complete

The time it takes to complete an activity, calculated as:
  • in Cancel activity and Activity details, multi-day activity is the duration of the finished segments

  • in “Complete activity” and “Close as Not Done”, multi-day activity is the result of subtracting the start time from the current time

  • in Reopen, multi-day activity is the minimal duration of a single segment based on activity type settings