Disabling Production Dates

If you prefer to control production dates manually, and do not want NetSuite to calculate production dates, you can disable this functionality. However, you must enter production dates manually on each work order.

To disable production dates:

  1. Go to Setup > Manufacturing > Manufacturing Preferences.

  2. In the Production Execution section, clear the Automatically Fill Production Start and End Dates box.

  3. Click Save.

    When you create a work order, the Production Start Date is editable.

    When you enter an Production Start Date, the Production End Date is editable.

Related Topics

Overriding Production Dates
Production Start and End Dates

General Notices