Reviewing the WOs That Didn’t Schedule Report

This WOs That Didn’t Schedule report displays the reasons Finite Scheduling processes fail. For example, incorrect workbench configuration.

To review work orders that didn’t schedule:

  1. Go to Advanced Manufacturing > Planning Reports > WOs That Didn’t Schedule.

  2. Click View beside the item you want to view.

    All work order items that did not schedule correctly (no asset assigned) appear on the report.

  3. To display the operations that are not scheduled, in the report, click the work order number.

    Note:

    Review this report daily and correct any work order errors to prevent further scheduling issues.

Related Topics

Reviewing the Production Data Entry Errors Report
Administrative Reports

General Notices