Creating a Planning Report

Use the following steps to create a planning report.

To create a planning report:

  1. Go to Advanced Manufacturing > Finite Scheduling > Work Order Management.

  2. Complete the Work Order Management page and then click Displays.

    For more information, see Finite Scheduling.

  3. On the Production Planning Reports window, select a Chart from the list.

  4. Select an Horizon Scale: Hour and Day, Day and Week, Week and Month.

  5. Select a Department.

  6. Select a Work Center.

  7. Click the calendar icon to select a Horizon Start date. Horizon start date must be a Monday.

    Note:

    To reduce processing time, keep horizon periods as short as possible. Generally less than one week.

  8. Click the calendar icon to select a Horizon End date.

  9. Enter a Work Order number.

  10. Select a Status.

  11. Click Display Report.

  12. After reviewing the chart, click Go Back.