Creating a Planning Report
Use the following steps to create a planning report.
To create a planning report:
-
Go to Advanced Manufacturing > Finite Scheduling > Work Order Management.
-
Complete the Work Order Management page and then click Displays.
For more information, see Finite Scheduling.
-
On the Production Planning Reports window, select a Chart from the list.
-
Select an Horizon Scale: Hour and Day, Day and Week, Week and Month.
-
Select a Department.
-
Select a Work Center.
-
Click the calendar icon to select a Horizon Start date. Horizon start date must be a Monday.
Note:To reduce processing time, keep horizon periods as short as possible. Generally less than one week.
-
Click the calendar icon to select a Horizon End date.
-
Enter a Work Order number.
-
Select a Status.
-
Click Display Report.
-