Adding a Rule to a Project Record

Add a project cost-to-cost percent complete rule to a project record.

To add a Project Cost Percent Complete rule to a project record:

  1. Go to Lists > Relationship > Projects > New.

  2. On the Financial subtab, click the Project Cost-to-Cost Percent Complete subtab.

  3. (Optional) Enter a valid non negative amount for the estimated Labor Cost Budget and Non Labor Cost Budget fields for this project.

    Note:

    You must do this step if you selected Pre-defined Value from Project in the Budget Basis list on the Project Cost Percent Complete Rule page.

  4. Check the Enable Project Cost-to-Cost Percent Complete box to run the project.

  5. In the Project Cost Percent Complete Rule list, select the rule you want to use to calculate the project completion percentage.

    Note:

    The default rule is selected automatically, but you can change it after you check the Enable Project Cost-to-Cost Percent Complete box.

  6. Click Save.

General Notices