How You Report an Operation Transaction Using Complete with Details
The complete with details mode enables you to complete an operation step directly from the Maintenance Dispatch List results rows.
You can review and edit the materials and resources for the operation transaction.
When reporting an operation transaction using the complete with details option, the flow consists of the following three train stops:
-
Asset train stop
-
Materials train stop
-
Resources train stop
-
Report Meters train stop
In a project-tracked organization, the header for each train stop also displays project number and task number for a transaction.
On successful reporting of the operation transaction, a confirmation message is displayed on the Maintenance Dispatch List page showing the transaction details. In case of error, a message with error details is displayed on the Maintenance Dispatch List page.
Asset Train Stop
In the Asset train stop, you can review the transaction. The following are the attributes in the Asset train stop:
Attribute |
Description |
---|---|
Asset |
The asset associated with the maintenance work order. |
Item |
The item associated with the asset. |
Serial Number |
The serial number associated with the asset. |
Work Center |
The work center associated with the maintenance work order operation. |
Work Order Quantity |
The planned quantity of the maintenance work order. |
Transaction Date |
The date of the transaction. The field is set to the current date and time. However, you can update it to a past date and time. |
Transaction Type |
The transaction type of the current transaction. |
Transaction Note |
Any note for the transaction. |
Attachments |
The attachments in the transaction. It can be of file, text, or URL type. |
Project Number |
The number of the project. This is applicable only for project-specific work orders. |
Task Number |
The number of the task. This is applicable only for project-specific work orders. |
Backflush Materials Train Stop
The Materials train stop enables you to review and edit the materials for the work order operation.
The Materials train stop is displayed:
-
If the Allow Quantity Changes During Backflush plant parameter is set as Both or Material
-
If there are lot or serial controlled components for backflush.
The following are the attributes in the Materials train stop:
Attribute |
Description |
---|---|
Status |
Indicates the status of the entered record. |
Transaction Type |
The default types will be Issue or Return. Issue will record a material issue transaction and install the asset in the hierarchy. Return will remove the asset from the hierarchy and record a material return transaction. Note: If the feature Issue or Return Materials for Work Orders Pending
Installation or Removal is enabled, then the Technician role will only
see types of Install or Remove. Install will only install the asset into
the hierarchy. Remove will only remove the asset from the hierarchy. The
Issue and Return transactions will be handled separately by the Stock
Clerk role.
|
Operation Sequence Number |
The operation sequence in the maintenance work order from which the material is derived. This can be the current operation or a previous automatically transact operation. |
Component | The component being added for reporting. |
Component Description | The description of the component being added for reporting. |
Basis | The basis type as defined in the work order operation for the component. For the manually added components, the basis is always Variable. |
Component Lot Number | The lot number of the component. |
Component Serial Number | The serial number of the component. |
Asset Number | The specific asset that will be installed or removed from the work order asset’s hierarchy. |
Parent Asset | The parent position in the work order asset’s hierarchy under which the material transaction line’s asset will be installed. It will default to the work order asset but can be manually updated to a child asset in the transaction line or by using the hierarchy viewer. |
Basis |
The basis type as defined in the work order operation for the component. For the manually added components, the basis is always Variable. |
UOM |
The unit of measure as defined in the component item or the organization item definition. |
Required |
The required quantity as defined in the maintenance work order for nonserial items. For serial items defined in the work order, the required quantity is 1 for each row and there can be as many rows as the quantity of item is required for the transaction. |
Previously Issued | The quantity of the component that's already issued to the work order operation. |
To Transact |
For nonserial items, this quantity is set to the quantity specified in the Required attribute with minimum as 1. For serial items defined in the work order, this quantity can only be 1. The default value is controlled by the organization’s plant parameter, Default Transaction Quantity, as detailed in the Implementing Manufacturing and Supply Chain Materials Management guide. |
Secondary Quantity |
The quantity is based on the item setup:
|
Secondary Quantity UOM | The unit of measure as defined in the item setup. |
Reservations | |
Additional Information region |
The additional information region is only enabled for serial-tracked and non-serial tracked operations if specific inventory flexfields have been defined and deployed. Additional details are covered in the Implementing Manufacturing and Supply Chain Materials Management guide. |
Revision |
The revision number of the component. The value is derived from the organization item definition. |
Subinventory |
Indicates the supply subinventory of the component. |
Locator |
Indicates the supply locator of the component. |
Use Common Inventory |
Check box to indicate whether the material is issued from the common inventory or from the project-specific inventory. |
Backflush Resources Train Stop
The Resources train stop enables you to review and edit the resources for the work order operation. The Resources train stop is displayed if the Allow Quantity Changes During Backflush plant parameter is set up as Both or Resources.
The following are the attributes in the Resources train stop:
Attribute |
Description |
---|---|
Status |
Indicates the status of the entered record. |
Operation Sequence Number |
The operation sequence in the work order from which the resource is derived. This can be the current operation or a previous automatically transact operation. |
Sequence |
The resource sequence as defined in the work order operation resources. |
Resource |
The resource being added for reporting. The field lists values that are concatenation of resource code and resource name. |
Type |
The type of resource as defined in the work order resources or in resource definition. |
Activity |
The resource activity as defined in the work order resources or in resource definition. |
Basis |
The basis type as defined in the work order operation for the resource. For the manually added resources, the basis is always Variable. |
UOM |
The unit of measure as defined in the work order resources or in organization item definition. |
Required |
The required quantity as defined in the work order resources. |
To Charge |
The quantity is set to the quantity specified in the Required attribute. |
Resource Instance |
Name of the resource instance. |
Record Meters Train Stop
The following are the attributes in the Record Meters train stop:
Attribute |
Description |
---|---|
Name |
Name of the meter. |
Code |
Code of the meter. |
Reading Type |
The type of the meter reading. The valid values are:
|
Direction |
The direction of the meter reading. The valid values are:
|
Displayed Reading |
The reading value displayed on the meter at the time of recording. |
Life to Date Reading |
The cumulative meter reading value that gets updated after each new meter reading entry. |
UOM |
Unit of measure of the meter reading. |
New Reading |
New meter reading value. |
Rollover |
Specifies whether or not the meter rollover is to be enabled. |
Reading Date |
The date on which the meter reading is recorded. |
Comments |
Any comment regarding the new meter reading. |
History |
The icon to view the meter reading history. |