Fleet Management

Create Work Assignment

This page is accessed via Fleet Management > Resource Management > Resource Schedule Instance > Actions > Create Work Assignment.

Run this action to create work assignments for the selected resource schedule instance. You can specify multiple shipments. This action is similar to the Create Work Assignment action that appears on shipments, but is run from the resource schedule instance. For particulars on the creation process, see Fleet and Bulk Planning.

Creating Work Assignments

  1. Enter a Work Assignment ID.
  2. Enter a Shipment ID.
  3. Click Save for each shipment ID you add to the work assignment.
  4. Click Create. You are taken to the other Create Work Assignment page where you can rearrange the order of the shipments.

Related Topics

Resource Schedule Instance

Resource Schedule Instance Actions and SmartLinks

Work Assignment

Create Work Assignment

Fleet and Bulk Planning