4.2 DIU Upgrade Phases

The following table shows the DIU upgrade process by procedure and estimated time. Actual times may vary with typing speed and system configuration. Perform the DIU upgrade on ELAP B first, then on ELAP A. Complete the phases in the order shown.

Table 4-4 DIU upgrade Phases

Phase Elapsed Time (Minutes) Activity Procedure
This Step Cum.

Connectivity setup

15

15

Set up connectivity to the MPS servers.

Procedure 1

Verify DIU upgrade

9

10

Verify this should be an DIU upgrade.

Procedure 26

Requirements check

2

5

Verify requirements for DIU upgrade are met.

Procedure 27

Assess readiness for DIU upgrade

15

20

Assess the server’s readiness for DIU upgrade.

Procedure 29

Pre-DIU upgrade health check

7

15

Run the syscheck utility to verify the MPS server is operationally sound.

Procedure 3

Pre-DIU upgrade system time check

5

60

Pre-DIU upgrade system time check.

Procedure 30

Pre-DIU upgrade Backups

22

75

Backup application databases and other pertinent information.

Procedure 5,

Procedure 31

Perform DIU upgrade

22

120

Run the DIU upgrade procedure on MPS B and A.

Procedure 32

Post-DIU upgrade health check

7

15

Run the syscheck utility to verify the MPS server is operationally sound.

Procedure 3

Accept the upgrade after successful soak period.

Note: User will not be able to perform backout procedure in case of any problem once the

upgrade is accepted.

4

This is done in a separate MTC

Accept the upgrade on both MPS-A and MPS-B after sufficient soak period of around 1-7 days (depending upon customer provisioning volume) to see that everything works fine after the upgrade.

Procedure 33

Post-DIU upgrade health check

7

15

Run the syscheck utility to verify the MPS server is operationally sound.

Procedure 3