Overriding status updates

If status updates have been submitted with incorrect information, you can override the update to change the values submitted by the resource. Optionally, you can notify the resource who entered the update. After you have changed the data entered for the update, you can later approve the update.

  1. Choose Tools, Approvals, Status Updates.
  2. On the Group By list, select whether to group the cards by Project, Resource, or Review.
  3. Select the projects for which you want to review status updates.
  4. Select the card or cards for which you want to override the status updates, then click Override.
  5. In the New column, modify the values for the fields you need to change for each card you are overriding.
  6. Optionally, mark the Notify Team Member by Email checkbox, if you want the team member who submitted the status update to receive an email about the overridden values.
  7. Click Override.