Assigning Resource Curves to Resource or Role Assignments from the Resources Assignments Page
You can assign a resource distribution curve to any resource or role assignment on activities with a duration type of Fixed Duration and Units/Time or Fixed Duration & Units.
To assign a resource curve:
- On the
Navigation Menu, expand
Resources and click Assignments. - On the Assignments page:
Tip:
You can also assign resource curves to resource or role assignment from the Activities page.