Assigning Resources to Unstaffed Activities
Use this procedure to assign resources to activities to fulfill staffing requests. Resources include the personnel and equipment that perform work on activities across all projects. Resources are generally reused between activities and/or projects.
Tip:
- Resource usage is are based on published data. The project must be republished before changes made to assignments within a project are reflected.
- You can also configure dashboard content to display the Open Requests for Resources portlet, which enables you to view staffing requests.
- The list of resources you can select from is determined by your resource security privileges and the current project association of individual resources.