Bar Type

Bar Type field

The types of bars shown in the Activities, Assignments, or EPS view Gantt chart.

Activities View

Current Bar: Spans the early remaining/actual start to the early remaining/actual finish for each activity, and indicates how the schedule is progressing according to the original plan.

Float Bar: Shows the total amount of time that an activity can be delayed without delaying completion of a project.

Free Float Bar: Shows the amount of time that an activity can be delayed without causing subsequent activities to be delayed.

Late Bar: Shows the late start to the late finish of an activity.

Percent Complete Bar: Shows the completion percentage of an activity.

Plan Bar: Shows the forecasted status of planned activities, and is used for simulating the outcome of the project schedule as part of project planning.

Project Baseline Bar: Shows the project baseline start and finish dates of an activity, and indicates how the schedule is progressing according to the original plan.

User's Primary Baseline Bar: Shows the primary baseline start and finish dates of an activity, and indicates how the schedule is progressing according to the original plan.

UDF Bar: Shows the amount of time spanning the selected Activity UDF start date and the Activity UDF finish date. UDF bars can be used to show a risk adjusted schedule using dates imported from Oracle Primavera Risk Analysis.

Pre Response Bar: Shows the pre response pessimistic dates of activities calculated by Oracle Primavera Cloud.

Post Response Bar: Shows the post response pessimistic dates of activities calculated by Oracle Primavera Cloud.

Assignments View

Current Bar: Spans the early remaining/actual start to the early remaining/actual finish for each activity, and indicates how the schedule is progressing according to the original plan.

Late Bar: Shows the late start to the late finish of an activity.

Plan Bar: Shows the forecasted status of planned activities, and is used for simulating the outcome of the project schedule as part of project planning.

EPS View

Current Bar: Spans the early remaining/actual start to the early remaining/actual finish for each activity, and indicates how the schedule is progressing according to the original plan.

Project Baseline Bar: Shows the project baseline start and finish dates of an activity, and indicates how the schedule is progressing according to the original plan.

Forecast bar: Shows the forecast start to the forecast finish dates, and indicates how the schedule is progressing according to the original forecast dates.