Configuring EPS View Gantt Chart

Configure Gantt chart options to determine how the chart will display.

To configure EPS view Gantt chart:

  1. On the "" Navigation Menu, expand "" Projects and click EPS.
  2. On the EPS page:
    1. Click the Views list and select a view.
    2. Click "" Customize View.
    3. In the Customize View dialog box, click the Gantt tab.
    4. On the Gantt tab, configure the options and click Save and Apply.

Tip:

You can also configure the Gantt chart from the View menu. Click Gantt Chart Options on the View menu and click the Gantt Chart tab.