Configuring Publication Service Settings for Projects
After enabling automatic publishing or adding a job to publish project data on a scheduled basis, perform the following procedure to configure settings for each individual project in Publication Services. Then, as you work, P6 automatically detects the changes to your project that trigger the publication of its data in the service queue.
To configure Publication Service settings for a project:
- On the
Navigation Menu, expand
Projects and click EPS. - On the EPS page:
Tip:
- By default, all projects are enabled for publication. You only need to modify the Enable Publication setting if you want to disable publication for a project or re-enable publication of a previously disabled project.
- Clearing the Enable Publication setting does not delete previously published data. You can delete published project data by selecting Delete Published Data on the Actions
menu in the EPS page.
- If you wish to modify publication settings for many projects at one time, you can display the Enable Publication, Last Published On, and Publication Priority fields as columns in your EPS view.
- If you want to publish Baseline data, you must also publish project data for the relevant projects.