Variance BL1 - Duration
Variance BL1 - Duration field
The duration between the activity's primary baseline duration and the at completion duration. Baseline variance columns only use data from visible activities. If you need to see variance for the whole project, remove any filters applied to the view.
Calculated as BL1 Duration minus At Completion Duration.